Question 1. 1.(TCO 8) In an overview of the major operations planning activities in a typical service organization, which of the following activities follows aggregate sales and operations planning? (Points : 3)
Process planning
Workforce scheduling
Master scheduling
Materials requirements planning
Order scheduling
Question 2. 2.(TCO 8) The main purpose of aggregate operations planning is to specify the optimal combination of which of the following? (Points : 3)
Workforce levels and inventory on hand
Inventory on hand and financing costs for that inventory
The strategic plan and the products available for sale
The workforce level and the degree of automation
Operational costs and the cash flow to support operations
Question 3. 3.(TCO 8) In conducting aggregate operations planning, there are a number of required inputs. Which of the following are inputs considered external to the firm? (Points : 3)
Competitor behavior and economic conditions
Market demand and inventory levels
Subcontractor capacity and current workforce
Economic conditions and current physical capacity
Raw material availability and inventory levels
Question 4. 4.(TCO 8) From an operational perspective, yield management is least effective under which of the following circumstances? (Points : 3)
Demand can be segmented by customer.
The product can be sold in advance.
Demand is highly variable.
Fixed costs are high and variable costs are low.
Demand is stable and close to capacity.
Question 5. 5.(TCO 8) A BOM file is also called which of the following? (Points : 3)
Product tree
Stocking plan
Inventory usage record
Production parts plan
Time bucket schedule
Question 6. 6.(TCO 8) Which of the following is an input to the master production schedule (MPS)? (Points : 3)
Inventory records file
The aggregate plan
The bill of materials
The exception report
Planned order schedules
Question 7. 7.(TCO 8) Which of the following is one of the main purposes of a MRP system? (Points : 3)
To educate personnel in basic work rules
To determine the amount of materials needed to produce each end item.
To stimulate the work force
To decrease labor requirements
To increase inventory accuracy
Question 8. 8.(TCO 8) Which of the following is an input to the master production schedule? (Points : 3)
Bill of materials (BOM) file
Inventory records file
Exception reports
Planned-order schedules
None of the above
Question 9. 9.(TCO 8) Which of the following is an input file necessary to run an MRP system? (Points : 3)
Exception report
Computer-aided-design files
Inventory records file
Personnel files
Planned order schedule
Question 10. 10.(TCO 8) In an MRP program, the program accesses the status segment of an inventory record according to specific periods called which of the following? (Points : 3)
Cubed time units
Time buckets
BOM units
Time modules
Time lines